24,000 sq ft.
14 weeks.

A Cat B fit-out over three floors for a London law firm, from bare Cat A to client-ready in one programme.

Client
Law firm
Location
Kingsway, WC2
Size
24,000 sq ft
Programme
14 weeks
Type
Cat B
The finished open-plan office with timber slatted ceiling

The
challenge

The firm's lease on its old office ended in June, and partners wanted a space that worked for client meetings first and desk work second.

The new building was a bare Cat A shell over three floors. There was no slack in the date: a late handover meant paying for two offices.

Empty Cat A office floor before the fit-out
Before Bare Cat A shell, week 1
The same floor after the Cat B fit-out
After Open-plan floor, week 14

Our
approach

We fixed the programme in week one and ordered the long-lead items (glazing, joinery and AV) before design sign-off, so they arrived on time rather than holding up the build.

Client floors were built first, so the partners could see the meeting suites finished by week nine while the open-plan floors were still on site.

Every Friday the firm's operations director got a one-page update against the programme.

A fitter fixing plasterboard to a new partition
Week 6 Client-floor partitions going up
Two site managers checking progress on a tablet
Every Friday Progress checked against the programme

The
finished
space

Three floors: a client suite with 26 meeting rooms on the first, open-plan teams above, and a tea point on every floor.

The
result

Handed over in week 14, a week before the old lease ended, with 26 meeting rooms, a client suite and 210 desks.

96% of site waste was diverted from landfill, and 40% of the existing furniture was reused.

Sample client quote
"We saw the client floors finished before the rest of the building was. That's when we stopped worrying about the date."
Managing Partner. Sample quote for this concept.